Fill in Parameters
|
When checked, it checks all the parameters in the section, except Simplified and Mass Calculation.
|
Plans
|
If checked, it uses plan lines in the recalculation.
|
(Plans) From
|
Enter or select a date that, together with the checked parameter Take into Account Only Current Deadline, determines the current plan lines.
|
Plan BOMs
|
If checked, it uses plan BOMs when recalculating. If they do not exist, active alternates of product specifications are used.
|
Reduce quantities
|
If checked, it reduces the quantities required in the lines of plan by reducing the quantities from stock or production.
|
Current Plan Only
|
If checked, only the current plan is used in recalculation.
If left unchecked, all plans with the Z - Finished status are used when recalculating.
Recalculates only plans of the same document type, unless the document type is entered with the plan document types in the settings of the current plan.
|
Stock
|
If checked, it uses available stock (inflows) at warehouses when recalculating. Only warehouses selected in the document type settings of the source plan are used.
|
Min. Stock
|
If checked, the minimum required stock of the warehouse is taken into account when recalculating.
|
Sales Orders
|
If checked, it uses approved sales orders when recalculating.
If a specific line of a sales order was already transferred to the plan, it is not used in the recalculation.
|
(Sales Orders) From
|
Enter or select the date that, together with the checked parameter Take into Account Only Current Deadlines, determines the current lines of sales orders.
|
Purchase Orders
|
If checked, it uses approved purchase orders when recalculating.
|
(Purchase Orders) From
|
Enter or select the date that, together with checked parameter Take into Account Only Current Deadlines, determines the current lines of purchase orders.
|
Allocations
|
If checked, it uses unissued quantities of the planned components of work orders, which have been released from the manufacturing specifications.
|
(Allocations) From
|
Enter or select the date that, together with the checked parameter Take into Account Only Current Deadlines, determines the current allocations in the work orders.
|
Work in Progress
|
If checked, it uses unfinished (not yet received to warehouse) planned quantities from the released work orders.
|
(Work in Progress) From
|
Enter or select the date that, together with the checked parameter Take into Account Only Current Deadlines, determines the current allocations in work orders.
|
Postpone Expired Deadlines |
If checked, expired deadlines will be postponed to selected date. |
(Postpone Expired Deadlines) To |
Enter or select the date that, together with the checked parameter Postpone Expired Dealines, determines the new date for expired deadlines. |
Alternate State
|
Select the status of alternates that will be used in the recalculation.
You can choose from:
- Preparation /Changing – the alternate is in the state of preparation or changing.
- Sampling / Testing – the alternate is in the state of sampling or testing.
- Validated – the alternate is validated and in production.
|
Dismantle into Sublevels
|
If checked, it dismantles specifications into the sublevel structure of products, when recalculating the schedule.
If left unchecked, the specifications are dismantled to the first level, that is, only to the directly adherent components.
|
To Level
|
Set the level to which the specification structure dismantling should be performed.
|
Take into Account and Calculate Deadlines
|
If checked, sets which schedules will be used in the recalculation. Fields From are available for parameters Plans, Sales Orders, Purchase Orders, Allocations, Work in Progress.
|
Simplified
|
If checked, simplifies the calculation of scheduling plan. All materials will be set at the start time of the plan and all products will be set at the end time of the plan.
The checkbox is visivle only if Take into Account and Calculate Deadlines is checked.
|
Mass Calculation
|
If checked, the faster way for scheduling plan calculation is enabled. It calculates the plan considering the levels not the dates.
It can be selected only, if the Simplified is checked or if Take into Account and Calculate Deadlines is not selected.
|
Take into Account only Current Deadlines
|
If checked, it uses only current data, that is data from the date entered in the field From, when recalculating.
|
Take into Account Order Quantity of Materials
|
If checked, it causes a minimum amount of material and packaging to be used when recalculating the requirements.
The surplus occurring due to packaging is used later on.
|
Take into account resources without scheduling |
If checked, resources are taken into account without scheduling them. |